But the public record has changed. A June 2026 Treasurer's report on 2025 development-charge transactions shows that the majority of that year's development-charge capital funding was allocated to Mulock Park. The same report shows Newmarket's combined development-charge funds ended 2025 with an internally tracked deficit of about $15.37 million. That is a Town-wide development-charge deficit — not a $15.37-million Mulock overrun.
Mulock Park is open. Now comes the less glamorous question: what did Newmarket actually spend to buy the property, build the park, restore the house and create the parking?
The first thing residents should know is that there has never been just one Mulock number. The land purchase, the park construction, the historic house and the off-site parking have been handled as separate pieces at different times.
The $24 million number was the land, not the finished park
Newmarket bought the Mulock property in 2018 for $24 million. The Town's supplementary capital budget added land-transfer tax, legal and due-diligence costs, restoration allowances and maintenance equipment. The total supplementary capital authorization was $28.85 million.
The Town financed the property purchase with a $26 million, 30-year debenture. That purchase happened years before the later park construction budget.
The $40 million park budget was never the whole project
In 2021, Council established a $40 million budget for the park itself. The Town's own 2023 report is very clear about what that number did not include: Mulock House and off-site parking were separate.
That matters because a comparison that starts with $40 million and ends with every later Mulock expense is not comparing the same scope.
$24 million purchase price for the property. The supplementary capital budget was $28.85 million after other acquisition, restoration and equipment allowances.
$40 million budget established for the park component. House work and off-site parking were excluded.
Town staff proposed increasing the park budget to $48 million. The same year, separate reports requested $11 million more for the house adaptive reuse and $3 million for off-site parking.
The Town later said Council had approved an $11.5 million budget for the Mulock House renovation, on top of earlier state-of-good-repair work.
Mulock Park opened in September with the skate trail, greenhouse and artist spaces, public art, restored Mulock House, café, gallery and parking now in use.
Why did the park budget rise from $40 million to $48 million?
The Town's 2023 report says the majority of the increase was driven by construction-market inflation. It cited roughly 30 per cent growth in GTA non-residential construction costs between early 2021 and the third quarter of 2022.
Staff also said the design team went through several rounds of value engineering to cut costs while keeping the approved amenities. The final 2023 request was an $8 million increase, bringing the park budget to $48 million.
That is a real cost increase. It is also different from claiming the original park budget simply doubled. The public record does not support that description.
Did Mulock Park directly raise property taxes?
The Town repeatedly said the capital increases for the park, house and parking could be funded without a direct impact on the property-tax rate. The 2023 park increase was funded through development charges and reserves. The house report identified federal gas-tax funding and Mulock reserve funds. The off-site parking report identified development charges and community-benefit charges.
That does not mean the park is free. Development charges, reserves and grants are still public money with rules about how they can be used. It means something narrower: the Town did not present these capital increases as a special property-tax increase for Mulock.
New records add another layer: the development-charge timing problem
On October 23, a reader pointed NewmarketStandUp to the Town's 2025 Treasurer's Statement of Development Charges and Reserve Funds. We checked the report against the numbers in this article.
The statement shows Newmarket's combined development-charge reserve funds began 2025 with $10.02 million. The Town collected $5.87 million in development-charge contributions, recorded $845,468 in interest expense and funded $30.42 million in capital and operating expenditures. The Town says the underlying development-charge position ended the year at a $15.37-million deficit, which continues to be tracked internally.
The report is explicit that the majority of 2025 capital funding from development charges was allocated to the Mulock Park capital project. Its detailed schedule lists about $20.25 million in development charges and another $6.49 million from other funding sources for Mulock Park Design and Construction in 2025.
That does not mean Mulock Park created the entire $15.37-million deficit. The development-charge system funds multiple growth-related projects. The Town's Parks & Recreation development-charge category also includes other park projects, trails, recreation facilities and a Magna Centre debenture. We therefore do not treat that category's balance as a Mulock debt.
Why did the development-charge money arrive later?
The Treasurer's report points to both provincial policy and market conditions. It says Bill 17 changed when some residential development charges are collected, moving collection from the building-permit stage to the earlier of occupancy permit or first occupancy. The Town estimates that can delay revenue by two to four years.
The report says those delayed funds are expected eventually to be recovered. It also identifies lower development activity, elevated interest rates, rising construction costs and softer market demand as pressures on development-charge cash flow.
The Town says it is now forecasting the longer-term impact of the deficit and examining measures that could include external financing or deferring capital projects until development activity improves.
Does this contradict the Town's explanation for the park cost increase?
Not by itself. These are two different questions.
The 2023 park budget report says the increase from $40 million to $48 million was driven mainly by construction-market inflation. It cited roughly 30 per cent growth in GTA non-residential construction costs between early 2021 and the third quarter of 2022 and said the project went through multiple rounds of value engineering.
The newer Treasurer's report is about how growth-related capital spending was financed and when the related development-charge revenue arrived. It adds financing context; it does not establish that the earlier inflation explanation was false.
And the Mulock House is still a separate piece
The Town's public record says Council approved an $11.5-million budget for the Mulock House renovation in 2023, on top of earlier state-of-good-repair work. The Town says the adaptive-reuse project is funded through a mix of grants, development charges and reserve funds, with no impact on property-tax rates.
That is why we are not combining a development-charge deficit, the house budget and the park budget into one headline number. They answer different financial questions.
There is also an operating cost
The 2023 park report said the operating budget was being phased in through $250,000 of assessment growth each year for five years. That is about $1.25 million when fully phased in, before programming costs. The report said the figure would be checked again as construction and programming became clearer.
This is one reason we asked the Town for a current annual operating forecast. The park is now open, so residents should be able to see what it costs to run, not just what it cost to build.
So the simple slogans do not work. “Mulock cost $40 million” leaves out major pieces. Saying “the $40 million park doubled” also mixes different scopes.
The fair question now is straightforward: what is the final actual spend for each component, what remains outstanding, and what will the entire site cost to operate each year?
The question is now bigger than the construction budget
The public record supports the Town's explanation that inflation materially increased the park budget. The newer Treasurer's report also shows that the timing of development-charge revenue created a separate financing pressure while major capital spending was underway. We will continue to update this article when the Town provides final project spending, current operating costs or further detail on how the development-charge deficit is being financed and recovered.
The records behind this article
2025 development-charge collections, expenditures, internally tracked year-end deficit, Mulock Park funding and the Town's explanation of delayed collections.
Open Treasurer's reportPurchase price, acquisition costs, restoration allowance and equipment.
Open Town reportThe $40 million 2021 park budget, the proposed $48 million 2023 budget, inflation explanation, funding and operating-cost plan.
Open Town reportSeparate house scope, $11 million additional spending authority request and funding sources.
Open Town reportSeparate $3 million parking request and funding sources.
Open Town reportTown states Council approved an $11.5 million house renovation budget in 2023.
Open Town releaseCurrent features and September 2026 opening.
Open Mulock Park pageSeptember 17, 2026: NewmarketStandUp asked the Town for current approved budgets, actual spending and commitments, contract amendments, operating costs, café and AGO financial terms, external funding and any unresolved claims or change orders.
September 29, 2026: Customer Service routed the request to Access and Privacy and advised that some records may require FOI. We still have not received a single reconciled final cost for all Mulock components.
October 23, 2026: A reader sent us the Town's 2025 development-charge statement. We independently checked the report and updated this article to add the funding and cash-flow context it documents. The reader's interpretation is not being used as evidence; the Town's report is.