Road condition matters, but it is not the only thing that can decide when a street gets rebuilt or resurfaced. Traffic, underground infrastructure, drainage, risk, maintenance timing and available capital can all matter. The Town publishes the broad rules and system-wide condition. What we still do not have is the current street-by-street condition file and ranked project list that would let residents test individual decisions for themselves.
Mayor John Taylor responded to our request on September 30. He said the volume and depth of our recurring information requests were becoming difficult for staff to compile and suggested a meeting to find a better balance. He also asked his office to locate the latest available report on road priorities as a starting point.
That is a fair concern. We told Taylor we would scale back the size of future requests. As of publication, however, the street-level pavement file and priority list we requested have not been supplied.
The important part is that we do not need to guess about the size of the problem.
The roads are in decent shape today. The forecast gets worse.
The Town's 2025 Asset Management Plan reported an average pavement condition index of 68 for the road network, which it classifies as good. It also reported that 99% of existing road assets were not due for replacement at the time of the baseline data.
But the same plan projects the average pavement condition index falling to 53 by 2034, with the share of existing road assets not due for replacement falling to 89%.
That does not mean Newmarket's roads are about to fail. The Town's own planning documents say something more measured: under constrained funding, more roads are expected to spend time in poorer condition, with more visible roughness, rutting and surface distress.
There is a real funding squeeze behind the choices
The Town's 2025 asset-management work identified an $81.8-million road capital funding shortfall over the 2025 to 2034 period. Roads were the largest tax-supported shortfall in that table, ahead of facilities, parks and bridges.
For 2026, Council's capital program includes $5.46 million for the Municipal Infrastructure Projects program. That money is not only for asphalt. The program also covers road rehabilitation and reconstruction, water and wastewater work, stormwater work and watermain relining.
That distinction matters. A street that looks ready for new pavement may be tied to underground work that makes it cheaper or smarter to coordinate the jobs instead of paving twice.
So what actually moves a road up the list?
The Town's asset-management policy says infrastructure decisions are supposed to be risk-based, systematic and repeatable. It says spending and priorities should be guided by risk, cost and service levels, with public safety taking priority.
The current Roads Asset Management Plan gives residents a few more clues. It identifies proactive maintenance such as crack sealing, resurfacing and repairs as ways to extend road life. It also specifically says roads with higher traffic volumes can be prioritized when poor pavement is creating slower travel.
The Town's public Road Improvements page says resurfacing is used to restore the surface on distressed roads. What that public page does not show is a current ranked table saying: this road scored X, that road scored Y, and here is why one was scheduled first.
A rough road can wait for a legitimate reason
Cane Parkway is a useful example of why a road project is not always just a paving job. The Town's planned reconstruction includes replacement of the watermain, sanitary sewer and storm sewer, changes to the lane layout, stormwater work, a multi-use path and sidewalk work.
That is exactly why a street-by-street comparison needs more than pavement condition. If underground infrastructure is nearing replacement, resurfacing the road first could mean paying to tear up relatively fresh asphalt later.
And not every road in Newmarket belongs to Newmarket
Residents also run into a jurisdiction problem. Some roads running through town are controlled by York Region rather than the Town.
Prospect Street is a simple example. The 2026 micro-resurfacing work between Gorham Street and Davis Drive was a York Region project. A resident can be standing in Newmarket and still be looking at a road whose rehabilitation schedule is not controlled by Newmarket Council.
What we cannot say
We do not have evidence that road resurfacing is being politically steered, that councillor requests are overriding engineering scores, or that work is being deliberately timed for elections.
Those were questions worth testing, not conclusions to start with. Without the street-level condition and priority data, an election-year analysis would be mostly storytelling.
So we are not doing it.
The question is transparency, not pothole politics
Newmarket has an asset-management system, a condition measure, a risk framework and a capital program. The Town is also openly forecasting more pressure on the road network over the next decade.
The missing piece for residents is simpler: when two streets both look bad, can they see why one is being fixed before the other?
If the Town provides the street-level pavement data or the latest priority report Mayor Taylor referenced, we will add it here and test the project list against it.
The records behind this article
Road inventory, replacement value, condition, service levels, risk and the 2034 performance forecast.
Open Town roads planIdentifies the $81.8-million roads capital funding shortfall for 2025 through 2034.
Open staff reportSets out the Town's risk-based, systematic and service-focused approach to infrastructure decisions.
Open policy pagePublic description of resurfacing, drainage work and work on distressed roads.
Open road programMunicipal Infrastructure Projects program covering road and underground infrastructure work.
Open capital budgetExample of road reconstruction being coordinated with water, wastewater, stormwater and active-transportation work.
Open project noticeExample of a road project inside Newmarket that is controlled by York Region.
Open construction noticeSeptember 29, 2026: NewmarketStandUp asked Engineering and Public Works for the street-by-street pavement-condition data, current scoring system, recent project lists, future priorities and the factors that can move a road up or down the list.
September 30, 2026: Mayor John Taylor replied that recurring requests at this level of detail were requiring substantial staff time. He offered to meet about a workable balance and asked his office to locate the latest report on the topic. NewmarketStandUp replied that the concern was fair and agreed to scale back the size of future information requests.
October 5, 2026: No street-level pavement file or ranked priority list has been received. This article therefore stops at what the public record can establish.